The Letham Park group have forwarded plans and photographs for the new Park development. This equipment has been selected to appeal to a broad range of people across the community. Work was meant to be completed by June 2009 however two issues arose- the sudden realisation that the works would have ruptured the gas pipeline and that the shelter requires planning permission. It is therefore unlikely that the work will be finished this year. Revised plans are shown below and news on the plannng application and progress will be posted here. I have also opened a forum topic to allow people to post their comments on the proposals.